Mine Production, Operation And Optimization For Limestone Project – PT. Gita Perkasa Mineralindo

Mine Production, Operation And Optimization For Limestone Project - PT. Gita Perkasa Mineralindo

This project was started on 13 January 2020 to 31 December 2022. The main objective of this project was purposed to optimize the production rate and costs. The initial program was aimed to investigate the potential issues that may affect the production rate and costs. Since the production rate can be optimized that the cost can be minimized. The costs were investigated from blasting, material collection, loading, hauling, crushing, stockpile management and barging. The optimization employed the mixed-integer linear programming (MILP). The results suggested that the costs can be optimized from IDR 168k per ton becoming IDR 48k per ton.